OUTSIDE FINANCIAL AUDIT  PROCESS

 

 

EFFECTIVE

DATE:

 

11/08/04

 

 
TABLE OF CONTENTS

PURPOSE

AUTHORITY

RESPONSIBILITY

DEFINITIONS

APPLICABILITY

PROCEDURES

128.01             AUDIT NOTIFICATION

128.02             AUDIT PROCESS 

REFERENCES

ATTACHMENTS

MANDATORY REVIEW DATE                                07/20/05

 

PURPOSE

 

To establish procedures for notification, review and responses to financial audits performed by non-department staff.

 

AUTHORITY

 

NRS 218.821

NRS 218.8235

NRS 218.8245           

 

RESPONSIBILITY

 

All Department employees are responsible for compliance with the procedures set forth in this regulation.

 

DEFINITIONS

 

FULLY IMPLEMENTED – The Department took all actions to satisfy the recommendations of the audit and the audit was corrected as of the date of the six-month report.

NO ACTION – The Department has not taken action to implement the recommendations of the audit.

 

PARTIALLY IMPLEMENTED – The Department has taken action to the extent possible to partially satisfy the recommendations of the audit as of the date of the six-month report and has taken steps such as requesting additional resources which may be necessary to implement the remaining recommendations. 

 

PLAN OF CORRECTIVE ACTION – A plan submitted by the Department which outlines the steps and timetables that will be taken to implement audit recommendations.

 

APPLICABILITY

 

This regulation applies to all Department employees responsible for audit processes, except employees of Silver State Industries.  Silver State Industries shall develop their own Internal Procedure governing financial audits.

 

PROCEDURES

 

128.01  AUDIT NOTIFICATION

 

1.1              When an employee receives verbal or written communication of a financial audit, they shall

within twenty-four hours notify the Chief of Fiscal Services.  The notification shall include:

 

·         The name and phone number of the auditor;

 

·        The date of the proposed audit; and

 

·        The scope of the audit.

 

1.2       Upon notification of a financial audit, the Chief of Fiscal Services will review the notification and determine the appropriateness of the request.  If appropriate, the Chief of Fiscal Services will designate an employee as a liaison for the audit.

 

128.02 AUDIT PROCESS

 

1.1              Written statement of acceptance, explanation or rebuttal

 

            1.1.1    Within 10 working days of receipt of the preliminary findings and recommendations,

the Director/designee will submit to the entity conducting the audit a written statement of acceptance, explanation or rebuttal concerning the audit findings.

 

1.2       Distribution of Audit Report

 

1.2.1           Within 10 days of receipt of a State or Federal audit report, the Department shall

submit one copy of the audit report and a management letter and the Department’s reply to:

 

·        The Director of the Department of Administration (if not originally copied);

 

·        Assistant Director of Support Services (if not originally copied);

 

·        Chief of Fiscal Services (if not originally copied);

 

·        The State Controller (if not originally copied); and

 

·        The Legislative Auditor (if applicable and not originally copied).

 

1.3       Plan of Correction Action (60-day report)

 

1.3.1        If the audit report contains any recommendations for corrective action the

Department’s designee must within 60 working days after the receipt of notification submit a plan of corrective action to the legislative auditor (if applicable), to the Department of Administration and to the entity that conducted the audit.

 

·        The Department may request assistance from The Division of Internal Audit to assist in drafting letters and suggesting methods to correct deficiencies.

 

·        If noted deficiencies can be corrected within available resources the

            Department will prepare a schedule to show how the audit recommendations     will be implemented; and a timetable for installing or completing the needed          adjustments.

 

·        If noted deficiencies cannot be corrected within available resources, the Department will prepare a budget request to meet the audit recommendations.

 

1.3.2        The Department will commence corrective action pursuant to the plan immediately after its submission.

 

1.4       Compliance Report (6-month report)

 

1.4.1        Five months after receipt of an audit and thirty days prior to the six-month reporting deadline, the Department’s designee will submit to the Director of the Department of Administration a status report and supporting documentation for implementing the corrective plan of action.

 

·        The report shall indicate for each recommendation the status as fully implemented, partially implemented or no action.

 

            1.4.2    Within 6 months after submission of the plan, the Department’s designee will submit to the entity who conducted the audit and the Department of Administration a report which specifies:

·        The extent to which the recommendations of the auditor have been carried out;

 

·        The extent to which the recommendations have not been carried out; and

 

·        The reasons for any failure to carry out the recommendations.

                                         

1.5       Interim reporting process for all Department audits.

 

1.5.1        All audits, correspondence, 60-day reports, and 6-month reports will be copied and submitted to the Department’s Chief of Fiscal Services to monitor the audit progress and to ensure the Department is complying with all audit time limits.

 

·        The Director will be notified by the Chief of Fiscal Services in the event the

                        Department is unable to meet the required deadlines.

 

1.5.2        The Chief of Fiscal Services will set up suspense files on each audit to notify the assigned Department’s audit contact 15-days in advance of the final due dates.

 

1.5.3        The completion date for Department responses shall be on or before 5 working days of the final due date to allow the Director/designee ample time for review and approval.

 

1.5.4        Interim reporting will continue on a schedule determined by the auditors or until all accepted recommendations have been implemented.

 

REFERENCES

 

SAM Chapter 2400

 

ATTACHMENTS

 

None.

_________________________________________________                      ___________________

Jackie Crawford, Director                                                                                Date

 

CONFIDENTIAL      ___                  XX

Yes                  No

THIS PROCEDURE SUPERSEDES ALL PRIOR WRITTEN PROCEDURES ON THIS SPECIFIC SUBJECT.